Plenty of Seattle projects have a construction permit application on file. Far fewer have an issued construction permit. The gap matters if you want to know what is going up on a given block this year. A project only starts building once the city issues its construction permit. Until then it can stay in review for months, sometimes years, with a permit application on file and nothing happening on site.
The permit record shows the difference. Below are the largest developments in Seattle that have an issued building permit, so work on the site can go ahead, ranked by the construction value on that issued permit. After that comes a second list of large projects whose construction permits are still in review.
How we ranked these
Early design estimates inflate a lot of published project values. A tower can show a placeholder figure of several hundred million dollars from an early design guidance filing years before anyone pours concrete. We skip those. Each value below comes from the construction permit the city has actually issued, which is the closest thing in the record to a real construction budget. That is why some numbers here read lower than headline figures you may have seen elsewhere.
Construction permit issued
Updated Nov 27, 2026.
| Rank | Address | Neighborhood | Building permit value | Units | Stories | Lead firm |
|---|---|---|---|---|---|---|
| 1 | 2350 6th Ave | Downtown | $371M | 891 | 46 | HB Management |
| 2 | 1600 9th Ave | Downtown | $224M | 404 | 30 | Hudson Pacific Properties / Pine Street Group |
| 3 | 747 Broadway | First Hill | $192M | 13 | PROVIDENCE HEALTH & SERVICES | |
| 4 | 1200 Stewart St | Downtown | $192M | 1,011 | 47 | Ankrom Moisan Architects |
| 5 | 1101 Thomas St | South Lake Union | $191M | 1,575 | 49 | Onni Group |
| 6 | 3020 NE 45th St | Ravenna | $170M | 796 | 8 | Quarterra |
| 7 | 3919 University Way NE | University District | $158M | 13 | Wexford Science + Technology | |
| 8 | 616 Battery St | Downtown | $138M | 442 | 46 | Holland Partner Group |
2350 6th Ave leads. At 2350 6th Ave in Downtown, the city has issued a construction permit worth about $371 million for a 46 story building with 891 homes from HB Management.
A 49 story tower in South Lake Union. 1101 Thomas St is a 1,575 unit development from Onni Group on the block the Seattle Times once occupied. Its issued permit values it at about $191 million.
Neighborhood towers, not just downtown. 2 of the 8 are outside the downtown core. 3020 NE 45th St, a Quarterra project in Ravenna, has a permit for 796 units. The University District also has a large permitted project of its own.
Still waiting on a construction permit
These projects are in the construction stage, but their building permits are still in review. We list them by the number of units proposed rather than a construction value.
Updated Nov 27, 2026.
| Address | Neighborhood | Units proposed | Stories |
|---|---|---|---|
| 1901 Minor Ave | Downtown | 1,007 | 40 |
| 5900 37th Ave S | Columbia City | 746 | 7 |
| 621 Stewart St | Downtown | 650 | 54 |
| 2301 7th Ave | Downtown | 622 | 30 |
The Downtown project at 1901 Minor Ave is the largest by unit count of anything in this stage, with 1,007 units proposed. Downtown has two tall towers that still need their permits, the 54 story 621 Stewart St from Kilroy Realty and the 30 story 2301 7th Ave. In Columbia City, 5900 37th Ave S would bring 746 units.