This is Part 2 of 2 for Building Permit Application. This portion is Part 2 which is the remainder of work not under review in Part 1 (Foundation, Demo, Underground) The Replacement school project proposes the remodeling of the Boys and Girls Club facility to contain Gym, Cafeteria, Kitchen, and Administration and Auxiliary spaces separated by an area separation wall from the New Two-Story Classroom and Library addition. No changes are proposed to the existing 3,500 sf Police substation extending West of the Boys and Girls Club building.
Submitted Jan 29, 2021Issued Jun 25, 2021Finaled Jan 19, 2024
This is Part 2 of 2 for Building Permit Application. This portion is Part 2which is the remainder of work not under review in Part 1 (Foundation, Demo, Underground). The project site occupies parcel 022135-5003 (new parcel number after lot combination) on 10.2 acres with R-2 zoning. The existing 58,000 sf school facility (located at 2502 N Orchard St) will be demolished to make way for new playfields and play sheds after the 27,615 sf Replacement Elementary School is constructed (to be located at 5136 N 26th St). The Replacement school project proposes the remodeling of the Boys and Girls Club facility to contain Gym, Cafeteria, Kitchen, and Administration and Auxiliary spaces separated by an area separation wall from the New Two-Story Classroom and Library addition. No changes are proposed to the existing 3,500 sf Police substation extending West of the Boys and Girls Club building.
Demolition Phase 2 scope includes demolition of Portable 2 including paving, capping existing unused utilities and required TESC including temporary storm facilities
Submitted Jul 7, 2022Issued Jul 15, 2022Finaled Oct 24, 2022
This is a 1,758 sf covered play shed building for outdoor play and is associated with the new proposed Downing Elementary School Replacement. Related SDEV20-0474.