All work described is subject to final LPC approved design. Product specifications provided in attached Narrative.
Excavate and form/pour footings and foundation. Frame new floor structure, exterior walls, window/door openings, roof structure, interior walls, stairs (int/ext), and porch. Install windows and doors in newly framed openings. Install new roof covering materials. Install wood lap siding, shingles at gable ends (as shown on design) and exterior trim. Rough in new electrical, plumbing, and mechanical systems. Install insulation in floor framing, exterior walls, and attic per present day code. Hang drywall on all wall/ceiling surfaces throughout. Install fixtures and finishes throughout newly constructed home to accommodate design.
**SEE LPC APPROVAL - HDR22-0020** Construct new 5 bed, 3 bath SFD with unconditioned basement. Includes plumbing and mechanical per approved plans. **05/05/2023 - FRR23-0145 APPROVED - Basement will no longer be conditioned space, updated letter from designer as per request from inspector.**
Submitted Jul 15, 2022Issued Mar 8, 2023Finaled Mar 22, 2024