Redevelopment ofthe South Recycling & Disposal Station for the new South Transfer Station Phase 2 (STS2) Project. The proposal includes: landfill closure elements, truck trailer parking area, a re-use drop-off area and store, recycling drop-off area, field crew quarters, decant facility, a sewer grit facility, a future material recovery facility, and others.
Land use application to allow 2, 1-story buildings for a public facility (Seattle Public Utilities, South Recycling and Disposal Station Redevelopment Project) . Parking for 81 vehicles proposed. Existing buildings to be demolished with paving and concrete to be removed and areas reconfigured and landscaped. Household Hazardous Waste building to remain. Determination of Non-Significance issued by Seattle Public Utilities.
Install factory-built structure accessory to solid waste transfer station and occupy as break room and locker room for recycling and disposal staff per plan.
Submitted Aug 23, 2013Issued Apr 25, 2014Finaled Oct 13, 2014
Install factory-built structure accessory to solid waste transfer station and occupy as break room and locker room for household hazardous waste staff per plans.
Submitted Aug 23, 2013Issued Apr 25, 2014Finaled Oct 13, 2014
Establish use as and construct new office building (West Crew Quarters building) for Seattle Public Utilities transfer station and occupy per plan. Mechanical included.(Construct 1 office 1 warehouse 2 accessory structures and surface parking and associated sitework and processing of 4 records under 6709571-CN)
Establish use as and construct new warehouse building (East Recycling and Reuse Building) for Seattle Public Utilities transfer station and occupy per plan. Mechanical included.(Construct 1 office 1 warehouse 2 accessory structures and surface parking and associated sitework and processing of 4 records under 6709571-CN)
Construct new accessory structure (Truck Wash) for Seattle Public Utilities transfer station and occupy per plan. (Construct 1 office 1 warehouse 2 accessory structures and surface parking and associated sitework and processing of 4 records under 6709571-CN)
Construct new accessory structure (Trailer Canopy) for Seattle Public Utilities transfer station and occupy per plan. (Construct 1 office 1 warehouse 2 accessory structures and surface parking and associated sitework and processing of 4 records under 6709571-CN)
Construct new office building (Crew Quarters building) Transformer pad retaining walls fencing and site improvements occupy per plan.(Construct 1 office 1 transfer trailer canopy 1 commercial building (Elec/ IT building) 1 pump station with water quality treatment facility and associated site improvements. Review and processing of 4 records under 7073602-CN)
Construct new pump station with water quality treatment facility per plan.(Construct 1 office 1 transfer trailer canopy 1 commercial building (Elec/ IT building) 1 pump station with water quality treatment facility and associated site improvements. Review and processing of 4 records under 7073602-CN)
Construct new commercial building (Elec/ IT building) occupy per plan.(Construct 1 office 1 transfer trailer canopy 1 commercial building (Elec/ IT building) 1 pump station with water quality treatment facility and associated site improvements. Review and processing of 4 records under 7073602-CN)
Construct new transfer trailer canopy occupy per plan.(Construct 1 office 1 transfer trailer canopy 1 commercial building (Elec/ IT building) 1 pump station with water quality treatment facility and associated site improvements. Review and processing of 4 records under 7073602-CN)