24 107342 TJClosedAPP COMPLETE APR 24, 2024 · ISSUED MAY 02, 2024 · COMPLETED FEB 06, 2025
Ext. 12/2/24 MD*
Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 4908. Starting at Comcast ped located near SW corner of 4912's property, crew will bore N approx 143' to a placed handhole and E approx 2' to 4908's property line. Route will finish on private property E approx 42' to 4908's connection. 1' of vertical clearance between bore path and all utilities. 5' of horizontal clearance between
bore path and paralleling storm/sewer/water main. Max pothole dimension 2' x 2'.