24 111834 TJClosedAPP COMPLETE MAY 16, 2024 · ISSUED MAY 28, 2024 · COMPLETED FEB 11, 2025
Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 4643. Starting at Comcast ped located near SE corner of 4701's property, crew will bore W approx 5' to 4701's property line. Route will finish on private property N approx 89' and W approx 38' to 4643's connection. 1' of vertical clearance will be kept between bore path and utility main/lines. 5' of horizontal clearance will be kept between bore path and paralleling water main. Max pothole dimension 2' x 2'.