25 104085 TJClosedAPP COMPLETE FEB 18, 2025 · ISSUED FEB 24, 2025 · COMPLETED OCT 20, 2025
EXT 10/10/25 for final. MD*
Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 4502. Starting at Comcast ped located near NW corner of 4511's property, crew will bore NW/N/E approx 133' to a placed carson on row boundary. Route will finish on private property E/N approx 74' to 4502's connection. Potholing is needed for project. 1' of vertical clearance will be kept from storm main, sewer and water lines. 8' of horizontal clearance will be kept from paralleling water main. 6' of horizontal clearance will be kept from paralleling storm main. Max pothole dimension 3' x 3'.