25 114770 TJClosedAPP COMPLETE JUN 16, 2025 · ISSUED JUL 01, 2025 · COMPLETED OCT 08, 2025
Underground horizonta boring using surface launched drill to install Comcast conduit to 12108. Starting at PED located near NW corner of 1330's property, crew will bore S and E approx 88ft installing 2inch conduit to a placed carson on ROW boundary. Route will finish on private property E approx 62ft installing .75inch conduit to 12108. Potholing for sewer lines, 1ft of vertical clearance kept. 10ft of horizontal clearance kept from paralleling water main.