18 107780 TNClosedAPP COMPLETE FEB 28, 2018 · ISSUED MAR 21, 2018 · COMPLETED OCT 04, 2024
Post Revision 7: Grind and overlay NE 10th Pl.
Post Revision 6: Illumination installation along Bel-Red Road
Post Revision-5: Remove trees in the right-of-way to accommodate the construction of the sidewalk along NE 10th Pl.
Revision-2&3: Storm sewer connections on Bel-Red Rd.
Revision-1: Frontage improvements along NE 10th and NE Bel-Red; Storm Water connections at NE Bel-Red.
Haul route only for the multifamily residential development. Subject to Clearing & Grading Permit # 17 118985 GD