21 132378 TJClosedAPP COMPLETE NOV 19, 2021 · ISSUED DEC 17, 2021 · COMPLETED SEP 12, 2025
ext 3/18/25 kb. EXT 4/23/24 KB. EXT 9/18/23 KB. EXT 8/19/23 KB. Crew to remove 3-phase distribution span between underbuilt transmission poles: 221769-167331 and 221769-167326; pole 221769-167326 will be removed when 230kV line goes in.Reconfigure pole 221769-167331 as a full-tension deadend and install guys/anchors. Confirm/verify that any anchors installed will meet clearance requirements to the Olympic Pipeline gas lines.