23 123661 TJClosedAPP COMPLETE OCT 16, 2023 · ISSUED OCT 20, 2023 · COMPLETED DEC 16, 2024
EXT 4/2/24 KB. Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 9810. Starting at telephone pole located near SE corner of 9820's property, crew will bore W/NW approx 39' and then hang dig N approx 4' to 9810's property line where 10" circular handhole will be placed. Route will finish on private property N/NE approx 29' to 9810's connection. Potholing on SE Shoreland Dr is not needed for project. 7' of horizontal clearance will be kept from bore path and sewer main.