24 113541 TJClosedAPP COMPLETE JUN 18, 2024 · ISSUED JUN 27, 2024 · COMPLETED FEB 11, 2025
EXT 1/21/25 requested by Comcast. MD*
Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 345. Starting at telephone pole located near SW corner of 328's property, crew will bore W approx 48' crossing under 105th Ave SE, N approx 26' to a placed carson and W approx 3' to property line. Route will finish on private property W approx 29' to 345's connection. 1' of vertical clearance will be kept between bore path and sewer/water/storm mains. Max pothole dimension 2' x 2'.