24 123969 TJClosedAPP COMPLETE OCT 16, 2024 · ISSUED OCT 24, 2024 · COMPLETED APR 23, 2025
Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 1136. Starting at Comcast ped located near S side of 1125's property, crew will bore SE approx 42' to row boundary. Route will finish on private property SE approx 2' to a placed carson and SE/E approx 65' to 1136's connection. Potholing is needed for sewer main/line. 1' of vertical clearance will be kept. Max pothole dimension 2' x 2'.