24 118481 TJClosedAPP COMPLETE JUL 30, 2024 · ISSUED AUG 01, 2024 · COMPLETED FEB 21, 2025
EXT 2/19/25 for final. MD*
Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 14430. Starting at Comcast ped located near SE corner of 14502's property, crew will bore NW approx 2' to row boundary. Route will finish on private property NW/SW/W approx 72' to a placed carson and N approx 29' to 14430's connection. Potholing on private property is needed. Max pothole dimension 2' x 2'. 1' of vertical clearance will be kept between bore path and water/sewer lines. 5' of horizontal clearance will be kept between bore path and water/sewer mains.