25 102471 TJClosedAPP COMPLETE JAN 30, 2025 · ISSUED FEB 06, 2025 · COMPLETED MAY 20, 2025
Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 5002. Starting at Comcast ped located near NW corner of property, crew will bore E approx 3' to a placed carson on row boundary. Route will finish on private property E/S approx 41' to 5002's connection. Potholing is not needed for project. 5' of horizontal clearance will be kept from both water lines. 6' of horizontal clearance will be kept from sewer line.