25 104866 TJClosedAPP COMPLETE FEB 24, 2025 · ISSUED MAR 07, 2025 · COMPLETED JUN 30, 2025
Underground horizontal directional boring using surface launched drill to install 2" Comcast conduit to 5260. All boring work will be on homeowner's private property from Comcast ped located near N corner of 5270's property, SE/NE approx 5' to a placed carson and NE/E/S approx 187' to 5260's connection. Maintaining 2' of vertical clearance from sewer main, 8' of horizontal clearance from water main and 9' of horizontal clearance from storm main. Work truck will need to be staged in front of 5260 in city row for duration of project.