21 116615 TJClosedAPP COMPLETE AUG 05, 2021 · ISSUED DEC 28, 2021 · COMPLETED SEP 12, 2025
ext 2/24/25 kb. **REV 2 - revised path and vault location field-approved by inspector. tjs 03/21/23** EXT 12/13/22 KB. Existing 3-phase OH distribution in the transmission R/W is a clearance problem for new 230kV line and is being removed from the R/W. New junction vault will be installed near existing pole 320154-167024.