25 106241 TJClosedAPP COMPLETE MAR 12, 2025 · ISSUED MAR 19, 2025 · COMPLETED JUN 13, 2025
Underground horizontal directional boring using surface launched drill to install Comcast conduit to 1913. Starting at Comcast ped located near NE corner of 1829's property, crew will bore W/N approx 86' installing 2" conduit along row boundary, avoiding water meters and maintaining 6' of horizontal clearance from storm main to a placed carson. Route will finish on private property W approx 65' to 1913's connection. Pothole on soft surface for sewer line is needed. 2' of vertical clearance will be kept.