25 114769 TJClosedAPP COMPLETE JUN 16, 2025 · ISSUED JUN 27, 2025 · COMPLETED SEP 26, 2025
Underground horizontal boring using surface launched drill to install Comcast conduit to 4427. Starting at PED located near S corner of 4501's property, crew will bore NE, NW approx 79ft installing 2inch conduit to a placed carson on ROW boundary. Route will finish on private property NW, NE approx 82ft installing .75inch conduit to 4427. Potholing for sewer and water lines, 1ft of vertical clearance kept. 5ft of horizontal clearance kept from paralleling sewer main.