25 114768 TJClosedAPP COMPLETE JUN 16, 2025 · ISSUED JUN 27, 2025 · COMPLETED SEP 30, 2025
Underground horizontal boring using surface launched drill to install Comcast conduit to 14914. Starting at PED located near SW corner of 14912's property, crew will bore E, N approx 70ft installing 2inch conduit to a placed carson on ROW boundary. Route will finish on private property N, E approx 30ft installing .75inch conduit to 14914. Potholing for water line, 1ft of vertical clearance kept. 7ft of horizontal clearance kept from paralleling storm main, 8ft from paralleling sewer main. Potholing on private property for storm and sewer main, 1ft of vertical clearance kept.