Shoring for (7) level subterranean parking structure. Shotcrete precon is required.
Revision #2 includes deletion of 240' of shoring at the West end of the South wall to facilitate Phase 1a for Neiman Marcus addition.
Submitted Jan 20, 2006Issued Jun 9, 2006Finaled Sep 4, 2008
Install a 24'x60' and a 28'x60' two-story modular construction office with an 8' X 60' upper and lower deck between them. Does not include clearing & grading.
Building is temporary and will be removed upon completion of the Bravern constructuction project.
Submitted Aug 2, 2006Issued Aug 17, 2006Finaled Oct 22, 2009