Construction of new elementary school building on the Birney Elementary School property. Related SDEV18-0039. Separate Plumbing and Mechanical permits are required for completion of this project.09092020 FRC20-0193 Approved to amend the demolition and routes of travel for the site. 09242020 FRC20-0193 Approved Phasing and egress plans reflecting sequencing of work. 07162021 FRC21-0129 Approved Bus canopy linking school north entrance to bus drop off area. FRC21-0163 (090821): change the previous design and structural system for the covered play structure
Submitted Feb 09, 2018Issued May 24, 2019Finaled Jul 15, 2022