6769232-PHIssuedSUBMITTED JAN 30, 2020 · APP COMPLETE JUL 16, 2020 · ISSUED OCT 12, 2021
Phased project: Construction of residential and retail building with two towers and below grade parking and occupy per plan. Deep foundations are under permit 6722431-CN (shoring and excavation).
6792886-CNCompletedSUBMITTED JUL 25, 2020 · APP COMPLETE JAN 20, 2021 · ISSUED APR 18, 2022 · COMPLETED MAY 20, 2025
Construct shoring and excavation for a future residential building per plan.
6811445-PHCompletedSUBMITTED NOV 19, 2020 · APP COMPLETE JAN 21, 2021 · ISSUED JUN 08, 2022 · COMPLETED MAY 21, 2025
Phased project: Construction of a residential building with below grade parking and occupy per plan. Mechanical is included.