Bryant Elementary School Replacement Part 1 of 2. This Permit Application is for foundations and underground work associated with constructing the foundations only. **Plumbing requires separate permit application** (Associated with early Grade and TESC SDEV23-0149)
Submitted Nov 30, 2022Issued May 2, 2023Finaled Oct 8, 2024
Remove Portable #3. Note portables 1& 2 will be retained as job trailers for the contractor and be permitted at a later date. Portables 3-7 will also be applied for concurrent with this portable and the main building (down to slab) for site security.
Submitted Aug 4, 2022Issued Sep 9, 2022Finaled Nov 24, 2023
Remove Portable #4. Note portables 1& 2 will be retained as job trailers for the contractor and be permitted at a later date. Portables 3& 5-7 will also be applied for concurrent with this portable and the main building (down to slab) for site security.
Submitted Aug 4, 2022Issued Sep 9, 2022Finaled Nov 24, 2023
Remove Portable #5. Note portables 1& 2 will be retained as job trailers for the contractor and be permitted at a later date. Portables 3,4,6,& 7 will also be applied for concurrent with this portable and the main building (down to slab) for site security.
Submitted Aug 4, 2022Issued Sep 9, 2022Finaled Feb 5, 2024
Remove Portable #6. Note portables 1& 2 will be retained as job trailers for the contractor and be permitted at a later date. Portables 3-5,& 7 will also be applied for concurrent with this portable and the main building (down to slab) for site security.
Submitted Aug 4, 2022Issued Sep 9, 2022Finaled Nov 24, 2023
Remove Portable #7. Note portables 1& 2 will be retained as job trailers for the contractor and be permitted at a later date. Portables 3-6 will also be applied for concurrent with this portable and the main building (down to slab) for site security.
Submitted Aug 4, 2022Issued Sep 9, 2022Finaled Nov 24, 2023
Bryant Elementary School Replacement Part 2 of 2. This Permit Application is for the remainder of the building not including foundations and associated underground work previously submitted under BLDCN22-0089. The 55,060 sf proposed project will contain Administrative, Middle and Elementary school Classrooms, Gym, Cafeteria, Music and Auxiliary spaces. **PLUMBING, MECHANICAL, AND ELECTRICAL SCOPES REQUIRE SEPARATE PERMITS**
Submitted Jan 4, 2023Issued Jun 15, 2023Finaled Dec 13, 2024
Install (1) double portable classroom modular building 28 x 64 per details provided. To be installed by Robbins and Co Housemoving Inc. 818 SW 142nd St, Burien, WA 98166 ROBBICH169NQ