Demolish Auto Office (550sf) First Student Office/Maintenance Bldg. (10 340sf) Starline Office (8 220sf) and Fuel Canopy (@600sf) per site plan and subject to field inspection STFI.
Submitted Apr 14, 2010Issued Apr 14, 2010Finaled May 23, 2012
Construct South Transfer Station and occupy per plan. (Phased project: Construct Transfer Station and Scale House / Review & process for 3 A/P's under # 6254759).
Submitted Sep 15, 2010Issued Jan 3, 2011Finaled May 22, 2012
Construct Scale House and occupy per plan. (Phased project: Construct Transfer Station and Scale House / Review & process for 3 A/P's under # 6254759).
Submitted Apr 7, 2011Issued Apr 28, 2011Finaled May 16, 2012
The applicant, the owner, the financially responsible party, the developer, the architect, the structural engineer, the geotechnical engineer and the contractor