Demolish existing structure down to ground floor diaphragm subject to field inspection. All grade level and below grade demolition to be included in the phase one shoring and excavation permit - 6084146.
Submitted Dec 19, 2005Issued Dec 19, 2005Finaled Jun 22, 2007
Construct Phase Two of Two King County/Goat Hill Administrative Office Building and occupy per plan. 2/12/07 mvc: Revision to energy code.revised 6/11/2007 - Shop drawings for curtain wall.
Submitted Apr 22, 2005Issued May 24, 2006Finaled Sep 12, 2007
Construct Phase One of Two Shoring and Excavation only Goat Hill Offices for King County. Also includes at grade and below grade demolition of existing structure.
Submitted Oct 12, 2005Issued Jan 20, 2006Finaled Jun 22, 2007