SDR - Demolish existing single family home and construct 5 new townhouses without parking. Permit process includes demolition permit, Streamlined Design Review, building permit, and unit lot subdivision.
Demolish existing single family home and construct 5 new townhouses without parking. Permit process includes demolition permit, Streamlined Design Review, building permit, and unit lot subdivision.
Construct west duplex per plan (Establish use as duplex and construct single family residence per plans. Review and process for 2 records under #6741447-CN)
Submitted Aug 02, 2019Issued Jun 30, 2021Finaled Jan 18, 2024
Construct east single family residence per plan. ( Establish use as duplex and construct single family residence per plan. Review and process for 2 records under #6741447-CN)
Submitted Dec 14, 2020Issued Jun 30, 2021Finaled Jan 22, 2024
Submitted Aug 02, 2019Issued Feb 01, 2021Finaled May 09, 2023
Other1 permit
003873-19PA
Unknown
Jul 22, 2019
—
—
—
Demolish existing single family home and construct 5 new townhouses without parking. Permit process includes demolition permit, Streamlined Design Review, building permit, and unit lot subdivision.
Submitted Jul 22, 2019
Permit data from SDCI
The full record
5 sections · with Pro
More about 717 Belmont Pl E
The land and its zoningPro
Parcel numbers, lot sizes, assessed values and zoning
2 parcels
What is inside the buildingPro
Floor areas from 2 of the 6 permits
12 areas
Sales historyPro
Recorded sales of this property, with the date and price of each
Press coveragePlus
News articles about this project, with the date of each
ContactsPro
The applicant, the owner, the financially responsible party and the contractor