How long do building permits take in Pierce County

Measured from the Pierce County public permit record, not estimated. Every figure below covers permits issued or decided from September 1, 2025 through September 1, 2026, and each one names the number of permits it rests on.

Design review
Fewer than 20 qualifying permits on record for this phase, so BuildVue publishes no figure for it.
Land use
38 days
typical days, application to decision
Half took between 8 and 61 days
62 permits, September 1, 2025 through September 1, 2026
Construction permit
25 days
typical days, application to issued
Half took between 8 and 88 days
1,433 permits, September 1, 2025 through September 1, 2026

Construction permits by project type

Project types with fewer than 20 qualifying permits are left out of this table entirely. These rows overlap, because a project counts under every type it contains, so one permit for apartments above ground floor shops is measured in both the multi family row and the retail row. Permits from September 1, 2025 through September 1, 2026.

Project typeTypical days from application to issuedHalf fall betweenPermits measured
Single family24 days8 to 77 days1,292
Institutional8 days6 to 384 days92
Multi family459 days398 to 894 days65

Methodology

Measured from a permit application date to its issuance date for construction permits, or its decision date for design review and land use permits. Only permits that build something are counted. Maintenance and minor alteration work such as roof replacements, tenant improvements and repairs is left out, because how quickly a city turns around a roof replacement says nothing about how long it takes to get a building approved. Permits with missing dates, permits reopened after an administrative closure, and permits open longer than 5 years are excluded as well. A figure is published only once at least 20 qualifying permits sit behind it, so a phase with a thin record shows nothing at all rather than a number built on a handful of permits. Every figure called typical on this page is the median, the middle permit once they are lined up shortest to longest, so a handful of unusually slow permits cannot drag it. These are the same permits shown elsewhere on BuildVue for Pierce County, so every number here traces back to a permit a visitor can look up. This page never compares Pierce County to another city. Different jurisdictions define application and issuance differently, and each one publishes a different mix of project sizes, so a shorter figure in one city would not mean its process is faster and a side by side ranking would not be a fair comparison.

Nearby cities

See building permit data for nearby Puget Sound cities.

Explore Pierce County permits on the map

See the individual permits behind these numbers on BuildVue's interactive map.